From when my Parents gave me my first train set for a Christmas present as a child, I have had an interest in model railways. I originally started in "OO" gauge, but have also built in "N" and "O" gauge. One layout I built was my exhibition layout "Holmehurst" which was in "O" gauge, and I exhibited it around the country. Photos of it can be seen by following this link.
I inherited some "OO9" rolling stock from my late father, including a loco I built from a white metal kit for him, and ever since living on our working narrowboat Hadar I have been thinking about building a "OO9" layout.
For those who do not know, "OO9" is "OO" scale, which is 4mm to 1ft, but the track and rolling stock are narrow gauge, equivalent to 2ft gauge in real life. Modelling-wise this means that I can used standard "OO" scale buildings, people, scenery etc. of which there is a far greater range of ready built items and kits to choose from, but it has the advantage that the reduced size of the track and rolling stock means that curves can be tighter than for standard gauge, without losing a realistic look within a restricted layout size.
I had thought about building a layout in our garden alongside our mooring at the
This is a full record of the building of the original layout, and having moved into a flat in Warwick and sold our narrowboat, this will now cover the building of the New Hadarford in our flat.
Please feel free to leave comments, I am always interested in suggestions or questions.
Tuesday, 23 January 2018
Monday, 22 January 2018
Final Timber Order Arrived
Wednesday, 17 January 2018
Cloudy Wallpaper
Bought a roll of this cloudy wallpaper from Homebase yesterday for £9.99 for a 10m roll.
Will be interesting to see how it looks behind the layout and, if successful, will be a cheap solution to backdrops for model railways.
Keith.
Tuesday, 16 January 2018
Sunday, 14 January 2018
New Lighting
This morning I temporarily installed the new permanent lighting, and removed the temporary lighting permanently.
Considering the temporary lighting has been in the hold for 10 years it hasn't done too bad. The temporary lighting was 4 12v halogen bulbs, 20 Watts per bulb, the new lighting is 4 LED light fittings, 2 Watts per fitting but equivalent to 25 Watts output each so brighter with less power consumed.
New lighting fitted temporarily but turned off, temporary lights on.
Temporary lights turned off, new lights on.
Temporary lights removed.
As can be seen from the photos then new lights are definitely brighter.
Keith.
Saturday, 13 January 2018
Hull Walls Finished
Port side finished today, it was lot easier today, and all the work was finished by 2.00pm.
Battens on the port side fixed in place.
Jo getting to grips with her new compact camera I bought her for Christmas.
The 2 large sheets of plywood fixed in place, with the socket box in place.
Just the last small piece to fit.
Both double sockets wired in and working.
The last piece of plywood on the port side fixed in place.
The final piece of plywood is fixed in place on the starboard side, that is enough for today.
Keith.
Friday, 12 January 2018
Starboard Side of Hull Nearly Finished
Busy day today, first we fitted all the battens to the starboard side.
First piece of Plywood fixed in place.
Second piece fixed in place with double power socket in it.
Just a small piece needed to finish the starboard side.
Keith.
Wednesday, 10 January 2018
Battens Cut Ready to be Installed and Another Addition to Engine Fleet
This morning Jo and I cut the battens ready for installation.
Unfortunately my first attempt to install the first batten failed! I managed to strip 3 Phillips No.2 bits trying to screw it to the steel bearers with the special self-drilling screws. Contacted the supplier ScrewFix and they recommend special bits for the job which I have ordered and will pick up tomorrow morning whilst I am out in Leamington Spa food shopping.
The engine at the back of my little railway arrived today, a great addition to my fleet of locos.
Keith.
Tuesday, 9 January 2018
First Delivery of Timber & Plywood
Today the first order of timber and plywood arrived.
Because of the lack of space in the hold we cannot store all the wood we need for the whole fit out, so this delivery is enough timber for the battens and walls for the walls below the gunwale.
I have also laid the mains cable in which will go behind the ply walls, which will give us a double socket on each wall.
Keith
Saturday, 6 January 2018
Friday, 5 January 2018
First Sections of Insulation Fitted
First 4 sections of insulation fitted, before bad light stopped play (and a coffee!).
Timber battens & plywood ordered for the hull section, just have to wait for it to arrive, but we should have all the insulation fitted below gunwale tomorrow.
Keith.
Thursday, 4 January 2018
Insulation
Sunday, 10 December 2017
Latest Update
Apologies for a lack of updates on the building of Hadarford recently. However we have now discussed with a neighbour the building of the railway room under the sheeting. They are keen to do the job for us, with our help. As they do have other work as a tree surgeon, they will be doing the work when they have time in the new year. As we told them we are not in any hurry, but it does suit them this time of year as their tree surgery works does drop during the winter time.
Both my wife Jo and I are now looking forward to the start of the build, which will be another step forward.
As we will also be away for Christmas this will probably be the last update until the new year, so may I wish you all a very Merry Christmas and a Happy New Year.
P.S. I wonder what Santa Claus will bring me?
Keith.
Sunday, 26 November 2017
Ballast Goes under the Shutts.
Since returning from our Autumn cruise, we had intended to put the bricks in the hold which we had picked up on our way into Birmingham, under the shutts for ballast. But unfortunately my prolapsed disc decided to come out again when we got back to our mooring and it has taken until today for my back to recover enough to consider putting the bricks under the shutts this morning, probably about 2½ tonnes filled up the space, the remaining ⅙ tonne, 167 kg will go around the water tank once we can get near it. The important thing today was to get the boxes of stuff we had temporarily stored on the pontoon whilst we were out back inside the boat especially now we are getting frost overnight.
Keith.
Saturday, 11 November 2017
Thursday, 9 November 2017
New Addition to Hadarfords Motive Power Fleet
Newest addition to my motive power fleet for Hadarford.
I was impressed with the maroon coloured Bemo loco that I inherited from my father and I have been watching out for a new one, which arrived today, in the blue livery. It has been well worth the wait.
Keith
Wednesday, 11 October 2017
Ballast
Friday, 15 September 2017
Lagging and Oiling
Keith.
Wednesday, 13 September 2017
Work in the Hold to Build the Model Railway Room
Today we started preparatory work for building my model railway room in the hold. First we had to sort out the rubbish we had accumulated, which went to the bins, then moved everything else as far forward as possible, which allowed us access to and removal of the first two shutts (floorboards) from the bulkhead at the saloon end of the hold.
It is in better condition than we thought it might be. Jo set about scraping and removing the loose bits, then painted the base of the walls. It is already for oiling tomorrow morning, then we can do under the next 2 shutts. We thought that whilst we had the shutts up it was lagging the main water pipe from the water tank in the bow with some pipe insulation, to stop the condensation which appears to be happening, so I popped to Screwfix to get some and have fitted the first lengths.
Keith.